Stadium Update

Repairs to Eagle Stadium and other improvements throughout the district were discussed at the monthly school Board of Trustees meeting on Aug. 25.

Continued collaboration between the school board and construction and design companies Pogue, PBK and Nelson Forensics have ensured that construction documents are sound and progress will continue in the right direction. The repairs have been divided into six stages, the first of which began on Aug. 5 and the last set to be completed in May. The first major repairs will be to the scoreboard for an overall cost of $250,000; new piers for the board were drilled Aug. 26. Subsequent phases include repairs to the press box, basement wall, visitor concourse and home and away side concourses. The board is also considering adding new skylight and roofing to the list of improvements to the high school following the food service-funded cafeteria renovation.